(PLANNING PERMISSION: LBS REG. NO. 23/AP/1862)
Following several key milestones achieved in May, including the removal of the existing concrete slab and underground fuel tanks, the completion of the piling mat at the Arebyte site, the installation and commissioning of the new Sylvan Grove substation, and the commencement of piling works for Block A, construction continues to progress well on site.
The second batch of site welfare cabins is due to be delivered in June, with fit-out works to the new welfare accommodation and relocation to the permanent site offices also scheduled to take place. Piling works for Block A and the piling mat at the existing petrol station area are due to complete, while groundwork operations will commence and highway extension works continue to progress.
We look forward to sharing further updates as the project progresses.