Project Background
Located in the London Borough of Southwark, Devonshire Place will deliver 941 best-in-class student bedrooms and 200 new on-site affordable homes. The development includes new commercial space and transport infrastructure upgrades, enhancing connections to surrounding areas through improved walking, cycling, and public transport links.
Positioned directly opposite the future Bakerloo Line Extension, Devonshire Place is designed to foster a vibrant new community and a thriving urban environment. Our commitment to enhancing the local area is reflected in high-quality public spaces, green areas, and a focus on well-being.
This mixed-use development will introduce a community hub, café, and open spaces, creating opportunities for residents—both new and existing—to connect and engage. With significant investment, Devonshire Place will support sustainable economic growth by providing high-quality affordable housing, premium student accommodation, new jobs, and enhanced public spaces.
Supporting the regeneration of Old Kent Road, the project strengthens its position as a key destination for living, working, and business, leveraging its central London location and the upcoming Bakerloo Line Extension to improve connectivity and economic opportunities.
Amenities
- Study Spaces
- Communal Lounges
- Gym
- Community Hub
- Café
- Green Spaces
Formation of Construction Phase Working Group
Before the construction phase commences, there will be an opportunity to attend a Construction Working Group round table discussion.
Newsletters will be published throughout the development lifecycle with regular updates.
Demolition Key Milestone Dates: Q2 2025 – Q3 2025
- Isolation of services/disconnections
- Soft strip
- Scaffold installation
- Hoarding installation
- Demolition of structures
- Removal of below ground obstructions
- Piling mat installation
Devonshire Place Project Delivery
As part of Regal’s commitment to complying with the London Borough of Southwark Construction/Demolition Management Plan (DMP/CMP) requirements, we have specialist consultants carrying out baseline environmental monitoring. By understanding environmental dust, noise, and vibration parameters, Regal can implement specific measures to minimise impact during the demolition and construction phases on sensitive receptors such as local businesses and residents.
Regal has appointed a transportation specialist to develop a logistics strategy for the demolition and construction phases. Careful consideration of traffic routing, control of site traffic, site entry/exit, vehicle loading, and unloading will form part of our CMP/DMP submission.
During our regular newsletter updates, there will be an opportunity to attend Construction Working Group round table discussions before the construction phase commences in Q2/Q3 2025.